CopperString

SecureEnergy - Project EnergyConnect

Scope: Local Industry Engagement and Procurement Initiative

Industry: Energy Transmission

Project Cost: $1.8 billion

SecureEnergy was awarded a contract to deliver the major portion of Project EnergyConnect (PEC); constructing a 700km 330kv transmission line from Wagga Wagga to the South Australian border. SecureEnergy collaborated with Hughes et al (HEA) to develop a Local Industry Engagement and Procurement program and target setting.

700 KM of Transmission Line

1,500 Estimated Towers

““The process of unbundling the Transmission Tower packages gave the project real insight into where
procurement opportunities could exist for not just Australian businesses but also the supply chain within the project footprint.””
— Client Reference

Overview

As a project over $500m, PEC has obligations to fulfill under an Australian Industry Participation Plan (AIP Plan) and to principally provide the Australian marketplace with a “full, fair, and reasonable opportunity” to participate in the project supply chain.

To ensure their obligations were met, SecureEnergy put in place several actions in the initial planning phase to ensure Australian standards were applied, and reasonable timeframes of competition had been offered. These actions included the early engagement of HEA to help facilitate the development and implementation of the Local Industry Participation Plan (LIPP).

The LIPP outlined key strategies that were further divided into actionable initiatives. One such strategy aimed to evaluate the Australian steel market, which led to the identification of an initiative to unbundle the transmission line packages. With the support of SecureEnergy procurement managers, competition from Australian companies was introduced.

As part of the unbundling process, discussions were held with the Australian Steel Institute (ASI) to assess the potential risks and opportunities this package could have in the Australian market.

SecureEnergy then undertook a Request For Quote (RFQ) process. HEA worked closely with the procurement team to define the scope and engagement, however once the RFQ was issued, HEA removed themselves from the procurement evaluation and final assessment.

Once the RFQ process was completed, the transmission towers package was awarded to an overseas company as foreseen, however the process of unbundling the package and testing the market enabled the identification of a handful of significant opportunities for Australian industry and SecureEnergy in tower inventory management, logistics and assembly, principally in a broader range of smaller scopes for local suppliers and skilled digital jobs for local workers.

“Thanks to a collaborative procurement team the project was able to provide a substantial body of work to underscore the projects commitment to the use of Australian suppliers in the supply chain, and identify where opportunities could be further explored in the construction phase of the towers for regional suppliers”
— Client Reference